《农村饮水安全工程监理工作总结》是一篇好的范文,感觉写的不错,希望对您有帮助,为了方便大家的阅读。
稿子汇,范文学习文库
篇一:江苏某农村饮水安全工程监理工作总结稿子汇 www.gaozihui.com
×××农村饮水安全三期工程 公文汇 www.gongwenhui.com
监理工作总结 公文汇 www.gongwenhui.com
月日 至年月 日 公文汇,办公文档之家
监理单位:总监理工程师:
法定代表人:
日期: 2011年1月10日
江苏省建设厅监制
监理工作报告
×××农村饮水安全三期工程在县委、县政府的的正确领导和×××农村计和规范要求顺利完成。我们×××监理有限公司受×××农村饮水安全工程建设工程处的委托,对×××农村饮水安全三期工程实施工程施工阶段的监理。现将监理工作情况回报如下:
工程概况
本工程包括×××××××××,其中×××饮水不安全人口为×××人,分布于10个村。×××饮水不安全人口为×××人,分布于×××个村。饮水不安全类型皆为苦咸水。由于长期饮用不安全水,给群众身心造成严重的危害,影响了项目区群众的生活和生产。本工程从区域供水接口处铺设输水主管网至各供水泵站,0.8Mpa (普通管):dn110 PE管×××米、dn160 PE管×××米思想汇报专题、dn200 PE管×××米、dn250 PE管×××米、dn315 PE管×××米,1.6Mpa(拖管) :dn160 PE管×××米、dn250 PE管×××米,螺旋钢管D108*5 ×××米、D159*6 ×××米、D325*8 ×××米、D219*8 ×××米。同时新建×××泵站一座,×××泵站一座,以提高供水压力,为项目区输送优质长江水,解决群众饮水不安全问题。该项目建设单位为×××农村饮水安全工程建设工程处,由×××市水利勘测设计研究院有限公司设计,×××建筑安装工程有限公司施工,×××监理有限公司监理。
我们公司在接受业主委托监理业务后,立即根据合同及有关规范、规定,成立总监负责制的现场监理机构。组织编制了本工程的监理规划以及相关的“监理细则”对三期工程的 个单位工程个分部工程的工程质量进行监督并协助业主对工程进度和造价进行控制。
监理过程
按照监理规划的要求,项目监理机构对×××农村饮水安全三期工程项目的施工阶段及竣工验收阶段实施监理,重点进行质量控制、进度控制和投资控制。在实施监理过程中,我们采用事前、网络事中、事后控制相结合的方法,并以事前控制(预控)为主,加强事中控制,做好事后控制,从而保证了该工程建设目标的实现。
工程质量控制
1、质量事前控制
(1)熟悉设计图纸、掌握施工要点、审核施工单位编制的施工组织设计,提出审核意见,督促施工单位健全质量保证体系,检查施工单位相关机械、人员的到位情况。
(2)加强对原材料的质量控制。对现场的钢材、水泥、砂、石、粘土砖、钢材等原材料均检查其质保书、合格证及检测资料。原材料送检情况:经国家工程复合材料产品质量监督检验中心检测给水PE管检验报告单 份,水泥检测报告 份,砂检测报告 份,碎(卵)石检测报告 份,钢筋(原材)力学性能检测报告份,砖检测报告份,M5砂浆、M10砂浆、C15、C20、C25、C30砼配合比通知单共份,其中M5砂浆抗压检测报告 份;M10砂浆抗压检测报告 份;C15混凝土抗压检测报告 份;C20混凝土抗压检测报告份;C25
土工(标准击实)检测报告 份;防腐防火涂装检测报告 份;焊缝超声检测报告份;范文写作土壤压实度实验报告 份;土工(环刀法)检测报告份,本工程所用材料合格证、质保单齐全,进场后都进行了抽检、复验、各项指标均达到设计及规范要求,合格率达100%。
(3)对特种工种上岗人员的资质审查。对焊工、电工、机械操作工等特殊的技术素质。
2质量事中控制
对管道沟槽开挖的深度和宽度进行控制,不得超挖基底,基槽内严禁泡水。
1.对PE管连接的质量进行现场巡视,控制热熔的温度以及冷却的时间,发
现问题及时指出,立即整改,确保整体工程达到合格要求。
2.对安装好的管线进行隐蔽工程验收,不合格达不到设计要求的不准进入下
道工序。对于特殊地段的管线埋深达不到设计要求的,我们在现场监督施工人员用混凝土对管线进行360°全包封。
3.加强旁站监理工作。对拖管工程的各道工序以及架桩支墩、支座和管道回
填等工序安排专人进行旁站监理,按照要求填写旁站监理记录。监理人员对施工作业过程进行有效地连续监控。监督施工单位严格按设计和规范标准进行施工。
4.每天定时或不定时的对正在施工的分项工程检验批进行巡视和检查。
5.对架桩过河、随桥过河钢管的内外除锈和防腐工作到生产厂家现场进行检
查,请检测中心检测技术人员到施工现场进行检测,全部达到设计要求。
3、质量事后控制
及时进行单元工程质量评定,对存在的缺限经业主、设计、监理、施工单位代表到现场共同确定处理办法,然后要求施工单位按规范处理,处理完成后经验收合格方可覆盖或进入下道工序。
监理采用的方法和检测的主要设备
本项目采用的主要监理方法包括:现场记录、最全面的范文参考写作网站发布文件、旁站监理、巡视检验、跟踪检测、平行检测以及内部协调。其中对于原材料、管材、设备、中间产站监理,如基坑(槽)验收、钢筋等实行监理工程师到场验收制度。
监理检测中采用的主要设备仪器有经伟仪、水准仪、试模、测绳和钢尺等。原材料和中间产品的检测、砼和砂浆配合比、沟槽回填的压实度、各种钢管焊接的探伤检测、PE管材等委托有检测资格的试验室进行检测。
工程进度控制
1、抓开工审批。监理工程师首先要求工程承包商提交施工组织设计,在施工组织设计中要有施工的总体进度计划。审查该进度计划是否满足合同文件工期的要求,是否具有可行性,保证措施是否完善。在项目进度实施中要有调整计划的应对措施,要从人、材、物等方面用事先控制的眼光来分析进度目标。总体进度目标计划确定后,在实施中根据总计划调整分部工程的实施计划。同时审查工程的进度计划是否满足业主方总进度计划要求。
2、抓施工设备、人员进场。施工单位与业主签定合同后,监理机构根据合同和投标文件的承诺,督促施工单位主要施工管理人员、主要机构设备及时进场,
篇二:农村饮水安全监理理总结范本 ***************农村饮水安全工程 监 理 总 结 报 告 ******监理咨询有限公司****** 二0一四年五月 1、工程概况 ******农村饮水安全工程涉及**村、**村、**村、**村四个行政村,受益村庄分别为**村大村、**村大村范文TOP100、**镇市场、秀篆中学、陈龙小学、**村发里自然村,**村大坪自然村。 ******农村饮水安全工程建设规模及建设内容:建设**镇**村、**村、**村、**村等6个行政村及镇内农村学校的供水工程。主要建设小型拦水坝6座,一体化净水器6套,清水池6座,以及铺设输配水管网。项目建成后将解决4834人及镇内学校学生1338人饮水不安全问题。 项 目 法 人:******人民政府 设 计 单 位:**设计设计有限公司 施 工 单 位:**有限公司 监理单位: **有限公司 1.1合同主要工程量: 本工程计划建设任务原设计建设**镇**村、**村、**村、**村等6个行政村及镇内农村学校的供水工程。主要建设小型拦水坝6座,一体化净水器6套,清水池6座,以及铺设输配水管网。经业主要求变更后建设小型拦水坝4座,一体化净水器4套,清水池4座,以及铺设输配水管网,变更后供水人口达到1164户7672人。 工程完成的主要工程量有四座拦水坝C20埋石砼122.32m3;60T/h净水器1套,25T/h净水器2套,30T/h净水器1套;清水池四座;铺设DN100以上管道6.0km,DN25~DN90管道24.58km。安装 入户管道1162户,铺设砂垫层3150.24m3,回填土方4876.44m3。供水范围达7672人。工程结算款为204.47万元。 2监理规划 2.1监理范围和监理依据 2.1.1监理处承担的监理工程项同范围为:合同项目的施工监理。 2.1.2监理依据 l、业主与监理单位签订的工程建设监理合同; 2、业主单位与承建单位签订的工程建设承包合同; 3、经审查批准的设计文什及技术联系单; 4、福建省现行的预算定额、取费标准及有关建设管理办法; 5、国家肯关政策、法律及经济合同法规; 6、国家、有关部门及地方制定颁发的施工技术及工程验收规范、规程、规定、质量榆验标准及建筑工程评定标准。 2.2监理处的组建 根据工程建设监理委托合同,我公司**市监理部于2012年3月16日对该项目实施监理。 监理部的工作指导思想:监理工作要始终以取得工程建设的整体最佳效益作为出发点和总体目标,并把工程质量放在首位。监理部的工作方针是:监督、管理、协调、帮助和服务。 监理部的基本职责和任务是:依照工程建设监理委托合同、施工 监理规范等,与建设、设计、施工等各方通力合作;帮助、检查、监督承建单位严格履行工程建设承包合同的职责和义务;充分运用监理的职责和技能,高效地工作,采用主动控制为主,被动控制为辅,两种手段结合的动态目标控制方法,运用全面质量管理手段和系统观点,做好工程质量、工程进度和工程投资控制,做好合同执行和信息管理,做好工程建设各方之间的关系协调,促使工程建设总目标得以更优的实现。 监理处组织:依据监理合同,监理机构为直线制,分总监、监理工程师、监理员三级。 临理处成员的分工职责: 1、总监理工程师:全面负责监理工作,对监理服务合同所承担的业务及行政负领导责任制,是监理部的第一负责人; 2、监理工程师、监理员:为监理部技术人员,在总监的领导下,承担相应专业的具体监理业务。 2.3监理部的职责和内容 1、督促设训计单位及时供应设计文件和图纸。根据监理委托合同要求,核对和确认设计文件、图纸和各项设计变更,或提出优化设计方而的意见; 2、加盖图文发送章,及时向承建单位签发设计文件、图纸和通知等,发现问题及时与设计单位联系,并将重要问题报告业主单位。 3、组织设计单位进行施工图技术变底; 4、协助业主单位会同设计单位对重大技术问题设计变更和优化 设计进行专题讨论; 5、审核承建单位对设计的意见和建议,会同设计单位进行研究,并尽快给予答复; 6、保管有关设计文件和资料; 7、审批承建单位提交的施工组织设计、施工技术措施、临建工程设计、施工详图、工艺试验成果等。签发补充的设计文件、技术要求等。答复承建单位提出的建议和意见, 8、审查认可承建单位或业主单位提供的用于工程的主材料、构件的出厂合格证、材质化验单等;检查工程采用的主要设备及管件材料是否符合设计文件或标书所规定的质量标准; 9、进度控制:参与和协助业主单位编制整个工程的控制性网络进度计划,提出各合同控制性进度目标;审查批准承建单位提出的施工进度计划,检查实施情况,督促承建单位采取措施实现合同目标要求;当计划变化时,及时提出调整网络计划的意见; 10、质量控制审查承建单位的质量保证体系和措旋;核实质量文件,对施工依据的合同文件、设计图纸、技术要求以及技术规范、标准、安装规程等进行检查和认可;对施工准备工作等进行监督,对工序质量采用旁站、巡视、拙检等手段进行监督、验收和签证,对隐蔽工程约请施工、业主、设计等四力联合验收;对施工中有违规范的地方,发出返工、整改通知,直至发布停工令;对施工质量进行评价; 11、投资控制:参与和协助业主单位编制投资控制性目标和合理投资计划;审核承建单位报审的工程量支付计量及新增或设计变更 篇三:某城镇农村饮水安全工程监理工作报告 XX市XX镇农村饮水安全项目工程 建设监理工作报告 监理单位:XXXXX XX年XX 月 XX日 工程名称:XX市XX镇农村饮水安全项目工程 批 准:XXX 审 查: 编 写: XXX XXX XXXXXXXXXXXXXXXXX市XX镇农村饮水安全项目工程建设监理工作报告 目 录 1 工程概况 ························································································································· 1 1.1 工程简介 ······················································································································ 1 1.1.1 工程位置 ········································································································· 1 1.1.2 工程布置 ········································································································· 1 1.2 工程建设相关单位 ···························································································· 1 1.3 主要工程项目及工程量 ···················································································· 1 1.5 主要工程技术指标 ···································································· 错误!未定义书签。 1.6 主要工程实施情况 ··································································································· 19 2 监理规划 ······················································································································· 20 2.1 监理工作依据············································································································ 20 2.2 监理范围 ···················································································································· 21 2.3 监理目标 ···················································································································· 21 2.3.1 投资目标 ······································································································· 21 2.3.2 进度目标 ······································································································· 21 2.3.3 质量目标 ······································································································· 21 2.4 监理组织机构及监理人员配置 ············································································· 21 2.5 项目划分 ····················································································· 错误!未定义书签。3 监理过程 ······················································································································· 22 3.1 施工准备阶段监理工作 ·························································································· 22 3.1.1 签发开工通知 ········································································································ 22 3.1.2组织设计交底 ··········································································································· 22 3.1.3 审查施工单位的开工报审 ··················································································· 22 1 XXXXXXXXXXXXXXXXX市XX镇农村饮水安全项目工程建设监理工作报告 3.1.4 参加第一次工地例会 ··························································································· 23 3.1.5 组织监理实施细则交底 ······················································································· 24 3.2 质量控制监理工作 ··································································································· 24 3.2.1 质量控制原则 ········································································································ 24 3.2.2 质量控制措施 ·····················································································(转载于: 在点 网:农村饮水安全工程监理工作总结)··················· 25 3.2.3 工程材料、构配件和设备的检测 ······································································ 26 3.3 投资控制监理工作 ··································································································· 27 3.3.1 工程计量 ················································································································· 27 3.3.2 工程变更后的投资控制 ························································ 错误!未定义书签。 3.3.3 主要投资控制措施 ································································· 错误!未定义书签。 3.3.4 完工决算 ·················································································· 错误!未定义书签。 3.4 进度控制监理工作 ··································································································· 28 3.4.1 进度控制原则 ········································································································ 28 3.5 竣工(完工)验收监理工作 ·················································································· 30 3.6 施工合同管理············································································································ 30 3.7 信息管理工作············································································································ 31 3.8.1 和业主的关系 ········································································· 错误!未定义书签。 3.8.2 和施工单位的关系 ································································· 错误!未定义书签。 3.8.3协调好参建各方的关系 ·························································· 错误!未定义书签。4 监理效果 ························································································ 错误!未定义书签。 4.1 质量控制效果············································································· 错误!未定义书签。 4.2 进度控制效果············································································································ 32 4.3 投资控制效果············································································· 错误!未定义书签。5 经验 ······························································································································ 32 2 XXXXXXXXXXXXXXXXX市XX镇农村饮水安全项目工程建设监理工作报告 5.1 经验 ····························································································································· 32 3 以上就是《农村饮水安全工程监理工作总结》的范文全部内容,讲的是关于监理、工程、单位、施工、设计、控制、进行、检测等方面的内容,希望大家能有所收获。
热门工作总结范文推荐: